IEC 62381:2024 — Factory and Site Acceptance Tests
The current IEC standard covers agreed scope, responsibilities and checklists for FAT, FIT, SAT and SIT of automation systems; the final site protocol remains project-specific.
Verify the installed system under agreed site conditions
Site acceptance demonstrates the delivered line in its destination environment after installation and commissioning prerequisites are stable enough for a controlled test.
Direct answer
A site acceptance test should verify installed equipment and connections, final utilities, safety and control interfaces, product-water and bottle conditions, integrated dry and production operation, agreed quality and output observations, training and handover records. It should use an approved protocol linked to the signed requirements and FAT disposition. The buyer and supplier need to confirm site readiness, representative materials, staffing, measurement methods and handling of issues outside the supplied equipment boundary before the test begins.
System focus 01
Commissioning is the controlled process of checking installation, energizing systems, proving utilities, adjusting machines and integrating the line. Formal site acceptance should follow only after agreed prerequisites and corrections are complete enough for a representative test. Recording this distinction prevents normal setup work from consuming the acceptance window and makes remaining commissioning limitations visible to both parties.
System focus 02
Measure or document power, compressed air, process and cleaning water, cooling, drainage, ventilation and environmental conditions at the line boundary while relevant equipment operates. A nominal plant utility rating may not reveal pressure loss, temperature change or simultaneous demand at the machine. Results outside the specified range need a responsibility and correction decision before they are used to judge equipment performance.
System focus 03
Site acceptance is the opportunity to verify final conveyors, retained equipment, factory networks, utility distribution, safety circuits and product paths in their installed arrangement. Check controlled starts, stops, starvation, blockage, alarms, interlocks and recovery. Where multiple suppliers are involved, the protocol should distinguish an equipment defect from an external condition without leaving the complete-line problem unassigned.
System focus 04
Use the agreed source or treated water, bottle, preform, closure, label, code and packing materials in suitable quantity. Record starting state, run periods, planned events, stops, rejects, counts, product and pack observations and operator interventions. Acceptance criteria must follow the contract and realistic site conditions; results should not be extrapolated to formats or materials that were not tested.
System focus 05
Acceptance is not only a run result. Confirm operator and maintenance training, safe operating procedures, cleaning and changeover guidance, approved manuals, drawings, software backups, parts lists, supplied spares and service contacts. Open items need classification, owner, due date and closure evidence. Final sign-off should state the tested conditions and any contractual reservations clearly.
Site acceptance sequence
Keep site-dependent evidence separate from adjustment activity while preserving one traceable acceptance record.
Inspect location, levels, anchors, guards, piping, wiring, labels, lubrication, access and all visible supply boundaries.
Measure relevant service conditions at named connection points and record external limitations before performance checks.
Verify rotation, settings, sensors, alarms, recipes, sanitation and controlled operation for each supplied system.
Test transfers, signals, speed coordination, interlocks, safety behavior and recovery with retained and new equipment connected.
Execute the approved production scenario with identified materials, measurements, event records and sampling.
Complete relevant operator and maintenance instruction and reconcile documents, tooling, backups and spares.
Record accepted results, reservations, open actions, due dates, evidence requirements and the final handover status.
The signed order and approved protocol control acceptance; this sequence is a planning aid rather than a substitute for contractual criteria.
Technical reading
Confirm the standards, guidance and legal requirements that apply to the project location and product before final design.
The current IEC standard covers agreed scope, responsibilities and checklists for FAT, FIT, SAT and SIT of automation systems; the final site protocol remains project-specific.
Buyer questions
Use these answers as a project-planning starting point. Final equipment and performance remain subject to the confirmed brief.
Commissioning prepares and adjusts the installed equipment for operation. SAT is the formal verification against agreed requirements after defined commissioning and site-readiness prerequisites are met.
Yes. Utilities outside the specified condition can limit operation or invalidate affected checks. Measure conditions at the defined connection point and assign corrective responsibility before disposition.
The contract and protocol should identify required formats and test depth. Untested formats should not be assumed proven; representative selection and later verification may be agreed for large format ranges.
Typical records include the protocol and data, deviations and closure status, training, delivered documents, software and parts, supplied spares, remaining obligations and the exact acceptance reservation or status.
Deep technical guides
Each guide answers one narrower project question and links the result back to complete-line scope.
Commissioning punch-list management turns observed defects, omissions and document gaps into controlled actions. Category should follow consequence for safety, hygiene, operation, acceptance and handover rather than cosmetic appearance or convenience.